Week 3 Work Team from Eureka, Smithville, Atlanta, Gridley, Fairbury

 

Fillmore Home

Working on the porch.    

Shingling the roof.   

Installing siding.   

Insulating the exterior walls.   

Sheetrocking the ceiling. 

Abbott Home

Drywall finishing.   

Mudding. 

Ledbetter Home 

The first truss is set in place.    

Just 35 minutes later …nearly half done.

 

Fixing equipment & building relationships.

 

Insulating walls.