Week Four work team from Lester, Forrest, Fairbury, Princeville, Gridley, Champaign, Bluffton, Goodfield and Taylor.
Fillmore Home
Siding work
Building the deck for the front porch.
Taping and mudding drywall
Abbott Home
Painting the walls and ceiling
Installing laminate flooring
Ledbetter Home
Shingles completed
Building the porch
Phillips Home
Footings are poured
Phillips foundation – ready to build
Laying out the floor joists